Guide

Commercial kitchen compliance checklist for UK cafés and restaurants

A UK commercial kitchen needs regular, documented checks on gas, extract, electrics, fire safety, water, pressure systems, refrigeration and pests. This checklist sets out what each item is, how often it is usually done, who does it and which law or standard sits behind it.

By the Fabric FM teamUpdated 30 October 202610 min read

Key points

  • Most kitchen compliance rests on a handful of laws: the Health and Safety at Work etc Act 1974, the Gas Safety (Installation and Use) Regulations 1998, the Regulatory Reform (Fire Safety) Order 2005, the Electricity at Work Regulations 1989, COSHH (for legionella) and the Pressure Systems Safety Regulations 2000.
  • Many frequencies come from British Standards and industry guidance rather than the law itself. Where guidance is risk-based, your interval should follow your risk assessment and your competent person's advice.
  • Insurers, landlords and environmental health officers will ask for evidence. A check that is not recorded is hard to prove.
  • In a leased unit, agree in writing who owns each item. Gaps usually appear where both sides assume the other is doing it.

How to use this checklist

This checklist is for cafés, restaurants, contract catering kitchens and similar food businesses in the UK. It covers building and equipment compliance, plus the main food safety touchpoints that overlap with maintenance.

Work through it site by site. For each item, record who is responsible, the date of the last check, the date the next one is due, and where the certificate or report is kept. Then look at the gaps. Missing certificates and expired dates are the most common findings in audits and insurance surveys.

Some items are fixed by law. Others are set by a British Standard, an industry guide or your own risk assessment. The table below shows which is which, so you can tell a legal minimum from good practice.

The compliance schedule

Frequencies below are typical. Your risk assessment, the manufacturer's instructions, your insurer or a competent person may require something different.

ItemTypical frequency or basisWho does itLaw or standard
Gas appliance and pipework safety inspection (catering gas safety record)Annually is the industry norm; maintenance per manufacturerGas Safe registered engineer with commercial catering competenceGas Safety (Installation and Use) Regulations 1998, reg 35; BS 6173
Gas interlock and ventilation checkAt each gas inspection; daily user check that extract is runningGas Safe engineer; staff for daily checkBS 6173; IGEM/UP/19
Kitchen extract (canopy, filters, ductwork, fan) deep cleanEvery 3, 6 or 12 months depending on daily cooking hours, or when grease deposits exceed limitsSpecialist ventilation hygiene contractorBESA TR19 Grease; RRFSO 2005
Canopy grease filtersCleaned frequently, often daily or weekly in busy kitchensKitchen staffManufacturer's guidance; TR19 Grease
Fixed electrical installation (EICR)Interval set by the inspector; commonly up to 5 years for commercial premisesQualified electricianElectricity at Work Regulations 1989; BS 7671
Portable appliance inspection and testingRisk-based; kitchen equipment often more frequent than office itemsCompetent personElectricity at Work Regulations 1989; IET Code of Practice
Fire risk assessmentReview regularly and after any significant changeResponsible person or competent fire risk assessorRegulatory Reform (Fire Safety) Order 2005
Fire alarm user testWeekly, a different call point each timeTrained staffBS 5839-1
Fire alarm serviceAt intervals not exceeding six monthsCompetent fire alarm engineerBS 5839-1
Emergency lightingMonthly short functional test; annual full-duration testStaff (monthly); competent person (annual)BS 5266-1
Fire extinguishersMonthly visual check; annual basic service; extended service or overhaul at longer intervalsStaff; competent technicianBS 5306-3
Fire suppression system over cooking lineService per manufacturer, commonly every six monthsApproved installer or servicerManufacturer's instructions; insurer requirements
Legionella risk assessmentReview regularly and whenever it may no longer be validCompetent personHSE ACOP L8; HSG274 Part 2; COSHH 2002
Water temperature monitoring and flushingMonthly sentinel outlet checks; weekly flushing of little-used outletsTrained staff or water hygiene contractorHSG274 Part 2
Coffee machine and boiler pressure system examinationAs set in the written scheme of examinationCompetent person (often an engineering insurer's surveyor)Pressure Systems Safety Regulations 2000
Refrigeration leak checksDepends on refrigerant charge in tonnes CO2 equivalent: from every 12 months to every 3 monthsF-gas certified engineerGB F-gas regulations
Lifts, dumb waiters and lifting equipmentThorough examination every 6 or 12 months depending on useCompetent person (usually insurer's engineer)LOLER 1998
Pest controlRoutine visits under contract, plus reactive call-outsPest control contractor and staffRetained Regulation (EC) 852/2004 Annex II
Food safety management system (HACCP)Daily records; review when menus, processes or equipment changeFood business operatorRetained Regulation (EC) 852/2004, Article 5

Gas, ventilation and extract

Gas is the highest-consequence item in most kitchens. Regulation 35 of the Gas Safety (Installation and Use) Regulations 1998 requires employers to keep gas appliances, flues, pipework and safety devices maintained in a safe condition. The regulations do not set a fixed interval for non-residential premises, but an annual inspection by a Gas Safe registered engineer is the accepted norm.

Gas and extract are linked. BS 6173 expects new and replacement installations to have an interlock, so gas cannot flow unless the mechanical extract is running. A blocked or greasy extract also creates a fire path from the cooking line to the roof.

Read more in our guides to gas safety in commercial kitchens and TR19 kitchen extract cleaning.

Staff accommodation counts

If you let a flat or rooms above the premises to staff or anyone else, landlord duties under regulation 36 may apply. That means a gas safety check every 12 months and a copy of the record given to the occupant.

Electrical safety

The Electricity at Work Regulations 1989 require electrical systems to be maintained so as to prevent danger. They do not name a test interval. In practice, an Electrical Installation Condition Report (EICR) to BS 7671 is how you show the fixed wiring is safe. The inspector records the date of the next inspection on the report.

Portable appliances, from stick blenders to microwaves, need inspection and testing on a risk-based interval. Equipment that is moved, washed down or used hard needs checking more often than a desk lamp. Staff should also do a quick visual check before use. See our guide to EICR and PAT testing for businesses.

Fire safety

Under the Regulatory Reform (Fire Safety) Order 2005, the responsible person must carry out a suitable and sufficient fire risk assessment and keep fire safety equipment maintained. Since October 2023, in England, every responsible person must record the full fire risk assessment, whatever the number of staff.

The usual testing pattern is a weekly fire alarm call point test, a six-monthly alarm service, monthly emergency lighting checks with an annual full-duration test, and annual extinguisher servicing. Many kitchens also have a wet chemical suppression system over the cooking line, which needs servicing by a competent contractor. Our guide to fire alarm and emergency lighting testing covers this in detail.

Water hygiene and pressure systems

Legionella control applies to any workplace with a hot and cold water system. HSE's ACOP L8 and HSG274 Part 2 set out a risk assessment, a written control scheme and routine temperature checks. Little-used outlets, such as a hand basin in a storeroom, need regular flushing. See our guide to legionella risk assessments for restaurants.

Espresso machines, steam ovens and some boilers are pressure systems. Under the Pressure Systems Safety Regulations 2000, the user or owner needs a written scheme of examination drawn up by a competent person, and examinations carried out at the intervals it sets. If you lease machines, check the contract to see who arranges this. Our guide to espresso machine pressure systems and PSSR explains the duties.

Ask for the scheme, not just a sticker

An inspection label on a coffee machine is not enough. Keep a copy of the written scheme and the latest examination report on file for each machine.

Refrigeration, F-gas and lifting equipment

Refrigeration that contains fluorinated gases needs leak checks by an F-gas certified engineer. How often depends on the size of the charge measured in tonnes of CO2 equivalent. Under the GB rules, systems at or above 5 tonnes need checks at least every 12 months, at or above 50 tonnes every 6 months, and at or above 500 tonnes every 3 months. A fixed leak detection system can extend these intervals. Many small plug-in units fall below the threshold, so ask your engineer to confirm each system.

If you have a goods lift, dumb waiter or hoist, the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) require a thorough examination by a competent person. Equipment that lifts people needs examining every six months. Equipment that only lifts goods needs examining every 12 months, unless an examination scheme sets otherwise.

Food hygiene and pest control touchpoints

Food safety law requires food businesses to put in place and keep to procedures based on HACCP principles. The Food Standards Agency's Safer Food, Better Business packs are a common way to do this in smaller kitchens. Maintenance links in at several points: fridge and freezer temperatures, probe thermometer calibration, dishwasher rinse temperatures and the condition of surfaces.

Annex II of retained Regulation (EC) 852/2004 requires adequate procedures to control pests. Most operators use a contractor for routine visits and keep a pest control file on site. Proofing work, such as sealing gaps around pipes and fitting door brushes, is often a maintenance task, so make sure contractor recommendations become jobs that get done.

Keep chilled food cold

In England, Wales and Northern Ireland, chilled food that needs temperature control must generally be held at 8°C or below. Many kitchens aim for 5°C or below to give a margin. Faulty fridges are a maintenance issue and a food safety issue at the same time.

Keeping records that stand up

Inspectors and insurers want to see three things: that the check happened, that a competent person did it, and that any defects were put right. For each item, keep the certificate or report, the contractor's details and the record of remedial work.

For multi-site operators, the challenge is consistency. One site may be fully up to date while another has an EICR that lapsed last year. A single schedule across all sites, with due dates and owners, is the simplest way to stay ahead. Our PPM schedule template for multi-site operators is a good starting point.

Fabric FM keeps every site's certificates, due dates and contractor visits in one place, so a missing or expiring item shows up before it becomes a problem. It is in early access now; see how it works on our compliance management software page.

This guide is general information, not legal advice. Check the current regulations and guidance, or speak to a competent person, for your premises.

FAQs

Common questions

What compliance checks does a UK restaurant need?

Most restaurants need gas appliance servicing and safety checks, kitchen extract cleaning to TR19 Grease, fixed wiring inspection (EICR), portable appliance checks, fire alarm, emergency lighting and extinguisher servicing, a fire risk assessment, a legionella risk assessment, pressure system examinations for coffee machines and boilers, F-gas leak checks on larger refrigeration, and pest control.

Is an annual gas safety certificate a legal requirement for a restaurant?

The law requires employers to keep gas appliances, flues and pipework maintained in a safe condition. It does not set a fixed interval for non-residential premises, but annual inspection by a Gas Safe registered engineer is the industry norm, is what HSE describes as a reasonable minimum, and is usually expected by insurers and landlords.

How often should a restaurant's EICR be done?

There is no fixed legal interval. The inspector sets the next inspection date on the report, and IET guidance gives maximum intervals by premises type, commonly up to five years for commercial premises. Kitchens with heavy use or harsh conditions may be given a shorter interval.

Do coffee machines need a written scheme of examination?

Espresso machines and other equipment that produce steam under pressure fall under the Pressure Systems Safety Regulations 2000. The user or owner needs a written scheme of examination drawn up by a competent person, and examinations at the intervals the scheme sets.

Who is responsible for compliance in a leased restaurant?

It depends on the lease and the equipment. The tenant usually controls kitchen equipment, extract, fire safety in the unit and water systems, while the landlord may control shared plant and common parts. Check the lease and agree in writing who does what.

How long should compliance records be kept?

It varies. Legionella records should be kept for at least five years under HSE guidance, and pressure system reports until the next examination at least. Many operators keep all certificates for the life of the equipment or tenancy so they can show a history to insurers and inspectors.